Beach Plaza of Lacey, NJ:
Strip the Stucco. Rebuild the Front. Keep the Stores Open.
Project Timeline: September 21, 2026 – November 20, 2026
The Beach Plaza exterior renovation project in Lacey Township, New Jersey, took the front of an active retail center down past the cosmetic layer and rebuilt the parts that actually hold the exterior together. Across roughly 50 working days, our scope included removing existing stucco and EIFS from the front section, dormers, and gables; inspecting exposed framing and sheathing; reconstructing portions of the elevation with new framing, plywood sheathing, T1-11 siding, soffits, fascia, aluminum capping, two new steel beams, and six-inch gutters; and coordinating the electrical work necessary to remove and later reconnect the storefront signs. Eduardo, Kyle, Jay, Milton, and Julio managed different pieces of the work in the field while Victor supported operations, giving us a project where carpentry, siding, structural work, painting, drainage, signage, and business access all had to stay in the same conversation. The finished storefront is the clean part. Getting there meant opening a building that still had businesses trying to make money on the other side of the wall.
Beach Plaza sits along South Main Street in Ocean County, and the project involved one commercial building with multiple storefronts operating behind the renovation area. That made disruption part of the scope whether it appeared on a proposal line or not. Customers still needed parking, tenants still needed visibility, deliveries still had to arrive, and the businesses had already survived enough seasonal disruption that ownership specifically wanted the heavier construction pushed until after summer. We were not renovating an abandoned strip center. We were rebuilding the face of a working one.
Waiting for Summer to End Before Opening the Building
The project began well before September with estimating, field review, scope development, storefront coordination, and a fairly practical decision about timing. Ownership wanted the businesses to get through the busy summer season without fencing, dumpsters, sign removal, and construction traffic taking over the parking lot. That pushed active production into September, giving our estimating and operations teams additional time to review the drawings, work through the building conditions, coordinate materials, and prepare the site before demolition began.
Our team also had to study what would remain once the stucco and EIFS came off. Exterior remediation is different from simply changing siding colors because the visible finish can hide framing, sheathing, water damage, and previous construction decisions that do not announce themselves until demolition exposes them. The contract therefore allowed the existing cladding to come off first so the framing and sheathing behind it could be inspected and any authorized repairs addressed before another finish covered the wall. You can learn plenty from drawings. Eventually somebody still has to open the building and see whether reality read them.
Municipal coordination ran alongside that work. Our office handled the primary permitting process with Lacey Township’s Building Department, including the inspections tied to the structural portions of the renovation. Lacey Township specifically requires permits for alterations, siding, roofing, and related construction work, so footing, framing, and final inspection requirements were part of the production schedule rather than something left for the end. The footing inspection passed during construction, and the project record shows the final building inspection scheduled for November 20. Permits are not the photogenic part of a façade renovation, but neither is explaining why somebody closed a wall before an inspector saw it.
One Retail Center, Eight Signs, and a Parking Lot That Still Had to Work
Storefront signage added another layer before active demolition could move through the full elevation. Existing signs and their electrical feeds occupied the same wall our crews needed to remove and reconstruct, so simply working around them was not a realistic plan. The approved additional scope called for disconnecting power, removing and disposing of the affected signs, and later reconnecting and testing power for the replacement sign installations. That required coordination between our team, ownership, tenants, and sign contractors rather than treating the signs as decorations somebody could move after the siding was finished.
The eventual revised electrical scope covered eight sign cabinets, with a separate electrical and sign-permit process running alongside the main building work. Not every storefront followed the identical path, either, with one salon retaining its sign without reinstallation through our project. Those differences matter in a commercial center because every tenant has its own operating needs, branding, electrical conditions, and expectations about when its name disappears from the building and when it comes back. A wall can be rebuilt in a sequence. Eight businesses rarely think in the same sequence.
Site logistics had their own rhythm. ProGreen was scheduled to provide the 30-yard dumpster and portable toilet, while a 16-foot storage container was staged for project materials. Ownership was notified about the coned work area and weekend staging before the September 21 launch, giving customers and tenants some idea of which part of the lot was about to become ours for a while. The idea was not to make construction invisible. It was to make it predictable.
The Stucco Came Off. Then the Real Building Showed Up.
Once demolition began, our crews removed the existing stucco and EIFS from the dormers, gables, and front portion of the building, exposing the construction underneath. That opened the wall for inspection and allowed deteriorated or inadequate framing and sheathing conditions to be addressed under the authorized project scope rather than hidden behind another exterior finish. Commercial façades have a way of accumulating history one renovation at a time. Removing the outer layer is often when everybody finally gets introduced to it.
The reconstructed front elevation incorporated new framing and plywood sheathing, rebuilding the structural backing before the finished cladding could return. Two new steel beams were also included in the project, with PVC trim used to finish those locations once the structural work was complete. That brought another trade and another inspection point into a project already moving through carpentry, cladding, electrical, painting, drainage, and sign coordination. A storefront renovation can look very tidy from across the parking lot. Up close, it is a crowded little ecosystem.
New soffit work and 2-by-6 fascia boards helped rebuild the roofline and exterior edges across the renovated section. Aluminum fascia and rake capping then protected and finished those exposed conditions while creating the sharper perimeter lines visible from the parking lot. Those pieces are partly aesthetic, but they also protect vulnerable edges where roof, wall, and trim systems meet. Water likes intersections. Most exterior renovation work is an elaborate effort to make those intersections less interesting to it.
Rebuilding the Front With T1-11 Instead of Recreating the Old Problem
Rather than reinstalling the removed stucco and EIFS system, the rebuilt elevation used T1-11 plywood siding across the designated front areas. The material gave the property a different finish while allowing the reconstructed wall and trim package to work together around the existing commercial architecture. New siding was only the outermost step, though. Its long-term performance still depended on the framing, sheathing, perimeter detailing, paint, and water-management work completed before and around it.
Material deliveries were coordinated through QXO, which supplies siding, trim, gutters, and other exterior building materials. Materials were scheduled ahead of the September 21 mobilization so the crews could move from demolition into reconstruction without turning the exposed storefront into a waiting room for the next delivery truck. QXO’s current product catalog spans siding, trim accessories, gutters, plywood, and related exterior materials, the sort of collection that becomes useful when one façade project manages to need several of those categories at once.
The exterior finish was then tied together with a selected gray-brown paint scheme. Ownership chose Valspar Gargoyle 8004-26E, matched into Sherwin-Williams SuperPaint Exterior Acrylic Latex in a satin finish for the siding, parapets, and three side doors, while soffit ceilings were finished flat white. A test patch on scrap T1-11 was planned before the larger paint order so everyone could see the color on the actual substrate rather than trusting a tiny chip under office lighting. Sherwin-Williams describes SuperPaint Exterior as an acrylic coating formulated for adhesion, color retention, and resistance to peeling and fading, which made it a practical finishing layer for an exposed commercial façade.
Getting the Water Off the New Front Elevation
The renovation also replaced the visible gutter system along the reconstructed frontage. New six-inch K-style gutters were installed and connected back into the building’s existing concealed PVC downspout piping, allowing the new exterior to manage roof runoff without requiring the entire drainage network to be rebuilt from scratch. The gutter color was selected to stay close to the finished siding tone rather than creating another visual line across the façade. When a gutter is working correctly, nobody standing in the parking lot should have much reason to think about it.
Those connections matter because replacing a wall without thinking about the water arriving from above would be a remarkably short-sighted renovation. New cladding, paint, fascia, and sheathing still depend on roof-edge drainage being collected and moved away from the elevation correctly. Gutters rarely get top billing in renovation photographs. They tend to become much more famous when they fail.
Fifty Working Days Later, the Plaza Looked Like a Plaza Again
By November, the heavy demolition and reconstruction work had given way to painting, remaining finish details, equipment removal, inspections, and the final walkthrough process. Dumpster, toilet, and storage-container pickups were scheduled as field operations wound down, while Eduardo prepared to review the remaining work toward closeout. The project’s Buildertrend record ultimately moved to Complete On Site, with the construction schedule running through November 20. The final municipal inspection had also been placed on the calendar, though the source record provided here does not document its final result.
For the tenants and customers, that transition is the part everybody waits for. Fences and containers disappear, signs return to where people expect them, parking spaces become parking spaces again, and the building stops looking like a project. For property management, however, the finished elevation becomes a maintenance asset that still deserves periodic attention. Paint condition, siding joints, fascia and capping, gutter performance, sign penetrations, and transitions between the renovated front and adjacent construction should all be watched over time rather than waiting until something dramatic makes the inspection unavoidable.
Commercial properties are particularly unforgiving about small exterior failures because the same façade has to manage weather, signage, tenant modifications, roof runoff, traffic, and years of maintenance work performed by different people. Keeping photographs, permit documents, paint information, sign-electrical records, and repair history together gives the next property manager something better than guessing what happened behind the wall. Buildings remember every renovation. Paperwork helps the humans keep up.
Does Your Commercial Exterior Need More Than Another Coat of Paint?
There is a point where exterior maintenance stops being maintenance. Repeated cracking, deteriorated stucco or EIFS, failed sheathing, questionable framing, damaged fascia, water intrusion, or storefront conditions that have been patched too many times usually deserve a closer look before another finish coat gets rolled over them. Beach Plaza required us to go past the surface, open the elevation, rebuild what needed rebuilding, and coordinate the work around businesses that still needed customers walking through their doors.
If your retail center, condominium property, multifamily community, or commercial building is dealing with failing exterior cladding, aging stucco or EIFS, deteriorated sheathing, structural concerns, drainage problems, or a façade renovation that needs to happen without shutting the property down, our team can help work through the project from investigation through closeout. Browse our completed projects to see how we approach exterior renovation throughout New Jersey, Pennsylvania, Delaware, and the broader Mid-Atlantic. When the front of the building needs more than another patch, contact our team at Lemus Construction and show us what is happening. Sometimes the cleanest way forward is to stop decorating the problem and finally open the wall.