Highlands at Glenmoor 2026 Roof Replacement

Community Roofing Replacement at Highlands at Glenmoor
Share this post

The Highlands at Glenmoor:
39 Buildings, 60 Homes, and Another 230,000 Square Feet Done Right

Project Timeline: February 16, 2026 – August 1, 2026

Community Roofing Replacement at Highlands at Glenmoor
Community Roofing Replacement at Highlands at Glenmoor
Community Roofing Replacement at Highlands at Glenmoor

Our Highlands at Glenmoor roof replacement renewed approximately 2,300 roofing squares, or about 230,000 square feet, across 39 buildings serving 60 Phase 2 units in Palmer Township near Easton, Pennsylvania. Daniel Arias led the project in the field while our estimating, office, customer-service, and production teams coordinated with KIPCON, the association, and property management through months of roofing, homeowner selections, permits, inspections, equipment movement, ventilation corrections, drainage work, and closeout. The new roofing uses GAF Timberline HDZ® shingles in Barkwood, backed by a GAF Golden Pledge® warranty program, with the 2026 scope carrying forward the kind of community-wide planning required when the roof work alone covers nearly a quarter-million square feet. GAF Timberline HDZ Barkwood

This was the Phase 2 roof-remediation program, covering 60 homes spread across 39 scheduled buildings rather than a single uninterrupted row of identical units. The contract work included complete roof removal, deck review and authorized repairs, new leak protection, underlayment, flashing, plumbing and radon penetrations, ventilation components, and other roof details required by KIPCON’s project manual. An executed addendum then expanded the drainage side of the work across all 96 units included in Phases 1 and 2, giving the larger Glenmoor roofing program one coordinated gutter and downspout standard.

That scale changes the nature of the job. A small roof can survive a fair amount of informal communication because everybody can usually see what is happening from the same parking space. Thirty-nine buildings require a plan, records, homeowner communication, engineering coordination, and a field team that knows what comes next before the current roof is finished.

 

Starting With KIPCON’s Plan and Our Own Site Study

The work began before bundles were loaded onto a roof. Our estimating and preconstruction teams walked the scheduled buildings, reviewing existing roof conditions, valleys, walls, plumbing penetrations, radon components, skylights, sun tunnels, attic ventilation, roof-mounted equipment, gutters, access routes, parking, landscaping, staging areas, and the places where construction would have to share space with residents. The engineering documents told us what needed to be accomplished, while those site visits told us how the work would actually fit into Glenmoor.

KIPCON provided the technical framework for the remediation and remained part of the approval process as buildings moved through completion. Its contract-administration work for community associations includes ongoing inspections, review of construction against specifications, and punch-list development, which is exactly the kind of structure a project this large benefits from. We want the engineering requirements understood before a crew reaches a condition, not reconstructed from memory while the roof is open and the weather app is getting interesting. KIPCON Contract Administration

Our own estimating information, photographs, building notes, homeowner records, material requirements, and internal handoff were then moved into Daniel’s production plan. That gave the field team something more useful than a total square count and a stack of drawings. Our multifamily and condominium roofing services are built around that transition from estimating to production because the larger the project becomes, the less forgiving it is when important information stays in somebody’s head.

 

One Community, 39 Different Roofs to Manage

The Highlands at Glenmoor roofing scope covered 39 buildings, but that does not mean we encountered one roof design 39 times. Each building carried its own collection of penetrations, skylights, vents, drainage paths, homeowner-installed components, landscaping, parking conditions, and previous repairs. Similar construction makes production more efficient, but familiarity is useful only if it does not turn into assumption.

The project had to move building by building while still operating as one coordinated capital program. Materials needed to arrive in the right sequence, residents needed notice, homeowner-specific roof items needed decisions before demolition, and KIPCON needed a clear path for reviewing work as it progressed. A schedule this large works best when the next several buildings are already being prepared while the active one is still under construction.

That sequencing also helped us keep the property from becoming one enormous construction yard. Completed areas could return to normal while equipment and crews shifted into the next active group. Residents were going to live with a large roofing project for months, but there was no reason all 39 buildings needed to look under construction at the same time.

 

Organizing the Jobsite for 230,000 Square Feet

The field operation required its own temporary infrastructure. Project records show Redbox handling dumpster support, United Site Services providing the portable restroom, and multiple JCB telehandlers along with an Equipter supporting material and debris movement over the course of construction. Those machines do not make the roof better by themselves, but they allow thousands of square feet of material to move without turning every bundle and every piece of tear-off into a manual trip through occupied spaces.

The equipment also had to move with the project rather than simply settle into the most convenient parking spaces for four months. Roofing materials, waste, delivery trucks, crew vehicles, resident cars, and common-area access all compete for the same finite amount of pavement. Daniel’s field coordination had to keep the machines useful without letting the machines become the project.

Daily cleanup mattered for the same reason. A condominium community is not a remote construction site that can sit untouched until Monday morning, and residents still need to walk, drive, receive deliveries, and use their homes after our crews leave for the day. Nails, packaging, damaged wood, old shingles, and loose material needed a controlled route off the buildings and out of the community.

 

Removing the Existing Roof and Seeing What Was Actually There

The base remediation called for complete removal of the existing roofing so the new system could begin at the roof deck. That gave our crews access to concealed conditions that cannot be responsibly evaluated through a layer of old shingles and underlayment. Where deck deterioration appeared, the project had an established process for documented and authorized repairs before new materials covered the area again.

This is one of the moments where roofing stops being theoretical. A roof can look tired from the ground for years, but once it is stripped, the plywood, penetrations, ventilation paths, flashing conditions, and old repairs get a chance to speak for themselves. Sometimes they are polite about it; sometimes they have apparently been waiting years for an audience.

Our job was to address the conditions the contract and engineering documents required without turning normal field review into a license to invent scope. Necessary repairs needed to be identified, documented, approved where required, and completed before the roofing assembly moved forward. The finished shingles only make sense when the surface beneath them is worth protecting.

 

Building the New GAF Roofing System

The association selected GAF Timberline HDZ® in Barkwood for the 2026 phase. GAF describes Barkwood as a rich neutral designed to evoke natural wood tones, with brown shading that works comfortably against beige, cream, gold, taupe, and other warm exterior palettes. In a community with dozens of separate rooflines, that kind of restrained color choice helps the buildings read as one property instead of asking each roof to become the main event. GAF Barkwood Roof Shingles

Timberline HDZ is GAF’s architectural shingle platform using LayerLock® technology and its enlarged StrikeZone® nailing area. GAF’s current technical information also identifies qualifying Timberline HDZ products with Class A fire performance and current impact-resistance testing, but the broader point at Glenmoor was not to install one premium shingle and consider the job finished. The field shingles had to work with the leak barriers, deck protection, flashing, ventilation, ridge components, and penetrations specified around them. GAF Timberline HDZ Roofing

The Phase 2 scope specified GAF WeatherWatch® and StormGuard® leak-protection components along with Tiger Paw™ roof-deck protection, new flashing, and related system accessories. Different roof areas face different water pressures, particularly around eaves, valleys, penetrations, and transitions, so the system had to be installed by location rather than by the theory that more product automatically means more protection. The useful roof is the one where every layer knows what job it is there to do.

 

Barkwood Across 39 Buildings

Color consistency becomes more important as the number of buildings increases. One slightly different roof on a single-family street can disappear into the neighborhood; a community capital project should look like the association made one deliberate decision. Barkwood gave Glenmoor a consistent warm-neutral roofline across the 2026 phase while still allowing the architecture, siding, brick, trim, and landscaping to carry their own visual weight.

That consistency depended on field workmanship as much as product selection. Course alignment, ridge lines, edges, transitions, penetrations, flashing, and the finish around accessories needed to stay disciplined from the first building to the thirty-ninth. Months of repetition can make a crew faster, but it can also tempt people to believe they have seen every possible condition already.

Daniel and our field teams kept building-level review tied to the production schedule so familiar details did not become casual details. The final building deserved the same roof standard as the first one, even if everybody involved could install Barkwood in their sleep by then. Repetition should build consistency, not complacency.

 

Ventilation Was Part of the Roof, Not an Afterthought

The scope included new ridge ventilation, static louvers, and other ventilation components where specified. Roof ventilation sits mostly out of sight once construction is finished, which means it receives far less attention from residents than the new shingle color. Heat and moisture remain considerably less impressed by curb appeal.

The project also addressed attic-fan conditions under the association’s current rules. Existing attic fans were removed as part of the roofing work, with electrical termination handled according to the project process, while homeowners wanting different future equipment had to follow the community’s requirements. This reduced the number of active roof penetrations and kept ventilation decisions connected to the engineered roofing system rather than allowing old equipment to dictate the new roof layout.

Future managers should preserve those ventilation records by building. A contractor arriving several years from now needs to know why a vent exists, why another one was removed, and how the attic was intended to move air after the 2026 work. Otherwise, the next improvement can accidentally undo the one everyone already paid for.

 

Bathroom, Dryer, Kitchen, and Radon Penetrations

Roof penetrations were another substantial part of the Phase 2 work. The base scope addressed plumbing and radon boots, bathroom and dryer vent caps, kitchen vent terminations, and other specified penetrations, while deficient homeowner-owned vent conditions could require additional correction. Each opening through the roof creates another place where roofing, flashing, mechanical systems, and homeowner responsibility meet within a few inches.

The internal homeowner guidance specifically addressed vents found to be improperly connected or terminating incorrectly. Those conditions needed to be corrected during reroofing rather than sealed back beneath a finished system and left for somebody else to discover later. The roof was already open, which is generally the best time to stop sending warm, moist air somewhere it was never supposed to go.

For long-term maintenance, these penetrations deserve their own place in the inspection routine. Pipe boots, exhaust caps, radon penetrations, and mechanical terminations experience different movement and wear than the surrounding shingles. A 230,000-square-foot roofing program can still develop a leak at a detail small enough to cover with one hand.

 

Coordinating Skylights and Sun Tunnels With Homeowners

Skylights and sun tunnels added a homeowner-specific layer to the project. The association roofing contract did not simply absorb every private opening into one community price, so affected owners received selection and financial-responsibility information before their building reached production. That kept individual decisions from becoming last-minute field questions after demolition had already begun.

The CST identifies VELUX skylight and sun-tunnel options, with fixed and venting configurations coordinated to the existing opening sizes. VELUX’s current deck-mounted skylight systems are designed to integrate directly with the roof deck and flashing system, which makes reroofing the logical time to coordinate replacement rather than cutting into a newly completed roof later. VELUX Deck-Mounted Skylights

Homeowners could also elect approved abandonment of certain skylight openings rather than replacement, with the opening closed as part of the roofing process and interior finishing remaining their responsibility. The important part was that an old skylight could not simply be ignored while a new warrantied roof was constructed around an uncertain opening. Penetrations require decisions; roofs dislike ambiguity.

 

Resident Communication Before the Crew Reached the Building

Homeowner forms were distributed, and start notices were hand-delivered before roofing reached the affected homes. The internal communication plan called for residents to receive notice several days before work began at their unit, giving them time to move vulnerable outdoor items, handle skylight-shade requirements, and prepare vehicles for nearby tear-off. That does not eliminate construction disruption, but it gives people a fighting chance to plan around it.

The roofing operation was designed to remain exterior-focused, without routine access through living spaces. Attic access needed for specified work could be handled from the roof rather than turning each home into an interior construction route. That matters at a community scale because sixty separate appointments inside sixty homes would create an entirely different logistical project.

Residents were also told that demolished roof areas had to be left weather-tight at the end of the working day. That is not an ambitious customer-service promise; it is a basic requirement of responsible roofing. Production counts only after the building is ready to survive the night.

 

Roofing Around Satellite Dishes and Heating Coils

Years of occupancy add things to roofs that were never part of the original construction drawings. Satellite dishes, heating coils, fans, cables, and homeowner-installed equipment slowly accumulate until reroofing forces everyone to decide what still belongs there. Glenmoor’s 2026 project addressed those components through association rules and homeowner responsibility rather than automatically reinstalling everything in the same place.

The homeowner guidance required roof-mounted satellite equipment to be removed and handled under the association’s relocation rules rather than simply drilled back through the new roofing. Heating coils followed a similar controlled process, with future reinstallation subject to community approval. Those rules reduce the number of uncontrolled penetrations going back into a system everyone has just spent substantial time and money replacing.

That policy is worth preserving after construction. A new roof can survive decades of weather and still be defeated surprisingly quickly by somebody with a drill, a tube of sealant, and absolute confidence that the association will never need to know. Roof access works better when permission and documentation come before the hole.

 

Replacing the Community’s Gutters and Downspouts

The executed 2026 addendum expanded the project beyond the Phase 2 roofs themselves. New 6-inch K-style seamless gutters with hidden hangers and 3-by-4-inch downspouts were specified across all 96 Phase 1 and Phase 2 units, replacing the smaller existing drainage components. That created a consistent drainage standard across the broader roofing program instead of leaving the new roofs to discharge into a patchwork of older systems.

The difference matters when thousands of square feet of roof are concentrating rainwater at the eaves. Larger gutters and downspouts still require correct pitch, secure attachment, clear outlets, and sensible discharge locations, but they give the community a drainage system designed around the renewed roofs above them. Our gutter and drainage services follow the same principle: getting water off a roof is only the first half of the trip.

For management, gutter maintenance should now be treated as part of the roofing investment rather than a separate housekeeping item. Leaves, debris, loose outlets, damaged leaders, and poor discharge can create staining, icing, erosion, wet siding, and water problems below a roof that is otherwise performing correctly. Gravity will happily move the water wherever the building lets it.

 

Palmer Township Permits and the Last Administrative Mile

Our office handled the permitting process with Palmer Township, where reroofing is specifically listed among projects requiring permits under the Township’s administration of the Pennsylvania Uniform Construction Code. Palmer’s Codes and Zoning Department processes permit applications and construction requirements, making the municipal record another part of the building-by-building closeout rather than paperwork detached from the actual roofing. Palmer Township Building Codes and Permits

The project tracker shows permits received overall, with Buildings 149 and 170 still carrying pending items in the current record. Final inspections also remained to be scheduled as the project moved into punch-list and administrative closeout. That distinction matters because the schedule records field completion on August 1, but the complete project file still needs every remaining permit, inspection, warranty, and release document to catch up with the roofs.

We do not need to pretend those two dates are the same. Construction can be complete onsite while closeout continues behind the scenes, particularly across dozens of buildings. A finished roof is the physical result; a finished project includes the paper trail proving how it got there.

 

GAF Golden Pledge® Protection

The Highlands at Glenmoor project is documented with GAF Golden Pledge® warranty coverage, and the warranty submission is already recorded as submitted and uploaded. For condominium, townhome, multifamily, and other non-single-family-detached structures, GAF’s current Golden Pledge materials describe a 40-year manufacturing-defect warranty term, a 25-year upfront non-prorated coverage period, and up to 25 years of GAF-backed workmanship coverage, subject to the registered warranty’s requirements, products, and exclusions. GAF Golden Pledge for Commercial and Multifamily Properties

That enhanced coverage is another reason the roof has to be thought of as a system. Golden Pledge eligibility depends on qualifying GAF materials, installation requirements, and certified-contractor participation rather than simply installing Timberline shingles and stapling a warranty brochure to the invoice. The underlayment, leak protection, ventilation, accessories, installation, and closeout documentation all become part of the same conversation.

The association should retain the final registered warranty certificate by building or project phase with the permanent closeout records. Our roof warranty guidance provides broader context, but the issued Glenmoor Golden Pledge documentation should control any future warranty decision. Marketing copy is useful; the certificate is what matters when somebody actually needs coverage.

 

Building-by-Building Approval Kept the Project Accountable

The contract tied billing to satisfactory completion at the building level, with association and engineer review before each completed-building invoice moved forward. A holdback remained in place until the broader project, required warranties, cleanup, lien documentation, damage resolution, and other closeout requirements reached final acceptance. We do not need to publish the financial details to appreciate what that structure did for the field operation.

It created a clear definition of progress. A building was not complete simply because the crew had shifted ladders to the next address. Workmanship, engineering review, cleanup, documentation, and corrections all had to follow.

That is a useful discipline on a long project because momentum can make unfinished details feel smaller than they are. The thirty-ninth building still needs a punch list even when everybody can already see the end of the summer. Close enough has a way of becoming permanent once the equipment leaves.

 

What Residents Should Expect From the Completed Roofs

Residents should expect a more consistent Barkwood roofline, renewed weather protection, updated roof penetrations, improved ventilation where included, and a drainage system coordinated with the larger roofing program. They should not expect the buildings to become maintenance-free simply because the capital project is complete. Wind, trees, ice, drainage debris, mechanical work, animals, and time continue operating without reference to the project schedule.

Residents can help most by reporting changes early. New ceiling staining, unusual skylight moisture, displaced shingles, loose flashing, gutter overflow, vent problems, or visible storm damage should be reported to management instead of investigated from a ladder. The association needs a good observation far more than it needs a resident conducting an unscheduled roof inspection.

Homeowners should also continue following community rules before installing or altering rooftop equipment. Satellite systems, heating equipment, solar components, mechanical work, and other exterior modifications can affect flashing, drainage, ventilation, and manufacturer warranty rights. The safest penetration is the one reviewed before anyone makes it.

 

How Management Can Extend the Life of the 2026 Investment

The association and MRH Enterprise should carry the project forward as a building-specific maintenance program, not one enormous folder labeled “2026 roofs.” Each building record should include the KIPCON specifications, permits, inspection approvals, approved GAF products, Golden Pledge documentation, photographs, deck repairs, ventilation changes, vent corrections, homeowner skylight or sun-tunnel decisions, gutter records, punch lists, and later service history. Thirty-nine buildings are manageable when the records know where they belong.

Professional roof inspections should be scheduled periodically and after major wind, hail, falling limbs, heavy snow, or ice events. Reviews should include shingles, flashing, valleys, ridge ventilation, static vents, pipe and radon boots, exhaust caps, skylights, sun tunnels, roof edges, gutters, downspouts, and locations altered by another contractor. The large Barkwood fields will be the easiest part to see and often the least complicated part of the inspection.

Drainage deserves its own maintenance schedule now that the larger gutter and downspout program has established one community standard. Gutters should be kept clear, leaders should remain securely connected, and discharge points should be watched for recurring erosion, staining, icing, or ponding. One blocked outlet can make a very large new roof look guilty of a problem it did not create.

Management should also maintain a roof-access log by building. The date, contractor, reason for access, photographs, penetrations, and repairs should be recorded whenever another trade works on the system. People change jobs; the roof should not be expected to remember for them.

 

39 Buildings Later, the Work Becomes Stewardship

The 2026 Highlands at Glenmoor phase brought together 39 buildings, 60 Phase 2 homes, approximately 2,300 roofing squares, roughly 230,000 square feet of roof surface, GAF Timberline HDZ Barkwood shingles, Golden Pledge coverage, KIPCON engineering, VELUX homeowner selections, ventilation corrections, roof-penetration work, new community-wide gutters and downspouts, Palmer Township permits, resident notices, heavy equipment, and months of building-by-building coordination. Daniel, our estimating team, office staff, customer-service team, roofing crews, KIPCON, property management, the association, and the residents all had a role in keeping those pieces aligned. The Barkwood roofs are what people will notice first, but the hidden work around airflow, drainage, penetrations, deck conditions, and documentation is what turns a large replacement into a long-term capital improvement.

The project schedule records onsite completion on August 1, with remaining punch-list, inspection, permit, and administrative closeout moving behind it. That is the point where construction starts getting quieter, and ownership becomes more important. The next useful work will be inspection, gutter cleaning, documentation, controlled roof access, storm review, and handling small changes before they become another major project.

The Highlands at Glenmoor 2026 phase now joins our growing portfolio of completed community roofing projects throughout Pennsylvania, New Jersey, and the Mid-Atlantic. Associations planning multi-building roof replacement need more than shingles and manpower; they need a team prepared to work through engineering, homeowner decisions, permits, drainage, ventilation, warranty requirements, daily access, and the hundreds of small details living between the first building and the last.

 

Planning a roof replacement, gutter program, or another exterior capital project for your condominium, HOA, townhome, or multifamily community? Contact Lemus Construction to discuss your buildings, engineering requirements, phasing, resident communication, manufacturer warranties, drainage, and long-term exterior plan.

Building Smarter

Subscribe for Project Insights & Updates

Get the latest tips, project highlights, and financing updates delivered straight to your inbox. Stay ahead with expert guidance from Lemus Construction for multi-family and commercial properties.

Related articles

Craig B.
5 years ago
Good work and service
Response from the owner:Craig, thank you for taking the time to provide your feedback! Let us know if we can ever be of further service to you.
Rob N.
1 year ago
Lemus descended upon our townhome community to replace our long lived roofs. The crew did everything they possibly could to protect gardens, screens, windows, etc. They worked incredibly quickly and efficiently. As part of their charge they repaired areas of damage when they found such, they brought areas around windows and chimneys into spec, and they connected exhaust vents and replaced skylights while making sure the attics vented properly through the gable vents and soffits. We also had very nice 6 inch gutters and downspouts installed. After each section they did the best they could to remove scattered nails both by hand and with strong rolling magnets. You know how you can tell a project went well? When you meet and become friendly with the crew. For instance: Harry R. Caesar Robin Pablo Carlos Christian Jesus Jose Mario... If you're looking at a roof project certainly give Lemus Construction a shot at providing a proposal.
Response from the owner:Rob, thank you for such a thoughtful and detailed review! It was a true pleasure working with your community on this roof replacement project. We’re so glad to hear that the crew’s care and repairs stood out to you. We’ll be sure to pass along your kind words to Harry, Caesar, Robin, Pablo, Carlos, Christian, Jesus, Jose, and Mario—they’ll be thrilled to know their hard work left such a positive impression. Thank you again for trusting Lemus Construction with your roofing, skylight, chimney, and gutter needs. We’re proud to help keep your community protected for years to come!
Bryan B.
6 years ago
Response from the owner:Hi Bryan, thank you for your feedback! We are glad you enjoyed your experience with us.
Mafer R.
4 years ago
I strongly recommend and encourage anyone looking for siding and deck replacement to contact Lemus Construction. They did a great job with my siding and provided the right price for the quality and service they offer. Their customer service was beyond professional.
Response from the owner:Thank you so much for taking the time to leave an excellent rating. We really appreciate your business. Please let us know what we can do for you in the future.
Marsie G.
4 years ago
This is the second time we've had Lemus do work on our house, and we will have them back again. Honest, hard workers that do top quality work.
Response from the owner:Hi Marsie, we are immensely grateful for your kind words! We strive to provide the highest level of service possible. Thank you for your continued loyalty and support.
Nicole B.
4 years ago
Lemus is a great company to work with from their ownership and administration to service- they have a great team. As a property manager, its crucial to have reliable vendors. My residents always comment about how hard Lemus works and their workmanship shows in the quality of their finished product. I highly recommend Lemus!
Response from the owner:Thank you so much for taking the time to leave us a rating. We feel very fortunate to have the opportunity to work with you!
Marianne C.
4 years ago
Response from the owner:Hello Marianne, Thank you so much for taking the time to leave us a positive rating!
Al R.
4 years ago
Lemus construction did an amazing job on our home. The project included a new roof, new sky lights, new siding, new trim, and a new composite deck. This was an extensive project, yet all of the work was completed within the timelines and budget as quoted. The crews were friendly and courteous and left the worksite tidy after each workday. A very competent foreman was on site directing the work each day. We can't say enough about how happy and satisfied we are with Lemus Construction and their beautiful restoration of our home!
Response from the owner:Hi Mr.Rauch, Thank you so much for taking the time to leave an excellent rating. We really appreciate your business. Please let us know what we can do for you in the future.
Kevin B.
4 years ago
Lemus is the number 1 company in this area. They are fast, responsive, courteous, clean, and willing to work with any request you may have. I would highly recommend this company for any home renovation or repair!
Response from the owner:Hi, Kevin. We really appreciate the kind words about our company and are so glad we could provide you with a positive experience! We strive to provide our best service for customers like you.
Bruce E.
9 months ago
The Lemus crew was quick and efficient. They protected the house and surrounding landscaping while removing the old roof. They repaired the rotting wood and finished off the project making the roof look better than it did when new. They installed a more efficient ridge vent as well as improved soffit vents to address to old roof's insufficient ventilation and moisture issues. None of the other roofing companies that quoted the job offered these solutions, even though they were aware of our moisture problem. I was impressed with the Lemus team's knowledge of roofs and the products available to address ventilation/moisture issues. Our attic no longer has that stale, musty smell from accumulated moisture, plus the roof looks great.
Response from the owner:Thanks for the support & letting us work on your home Bruce! It was our honor and we appreciate you for taking the time to share such a detailed review. We're glad the team was able to address the ventilation and moisture concerns & it means a lot to hear that the results are already making a difference. We truly value your trust with Lemus Construction & don't hesitate to reach out for any concerns or future projects. Best, The Lemus Team
DAVE T.
4 years ago
Great company, I highly recommend! Complete roof tear off (2 layers) and replacement on a 2800sf colonial including removal of old solar panels and skylight replacement as well as gutter replacement completed in under 2 days. Extremely professional and knowledgeable crew and management. They are efficient, neat, courteous, and meticulous. The finished product is amazing, price and financing options are great, and the Warranty is the best in the business.
Response from the owner:Hi, Dave. We are thrilled to learn that you had a positive experience with us! Thank you so much for the kind review.
Joe A.
1 year ago
Response from the owner:Hi Joe, thank you for the 5-star rating! We appreciate you taking the time to support our team—your feedback means a lot.
Quentin
3 years ago
Response from the owner:Quentin! We appreciate the 5 Stars!
Guerin H.
5 years ago
Servicio profesional
Response from the owner:Hi Guerin, Thank you for your positive feedback! We are at your service.
Scott P.
9 years ago
Response from the owner:Hi Scott, thank you for the rating! Please feel free to call our office if you need anything in the future.
Roxanne K.
2 years ago
The crew did a job to repair water damage. They were very thorough, neat and went above and beyond to make the repair.
Response from the owner:Hi Roxanne, thank you for the kind review! We love hearing that our crew went above and beyond to ensure your comfort and satisfaction. Any business would be proud to receive that kind of feedback, and we're no exception. We truly appreciate you taking the time to share your experience.
Fran H.
1 year ago
We had a disastrous situation by a previous contractor (I'd love to name them but won't) on our commercial roof. We were expecting a full replacement would be needed. Victor met with us on site. We walked the entire roof and he pointed out the problem spots and explained in detail, the work that would be needed to remedy our issues. His estimate was very fair and he was up front about some potential additional work that might be needed that could not be determined at the time of the survey. Those costs came in at a minimum when the work was done. Lemus's professionalism & craftsmanship was incredible from the start of the process to the end. Our issues are completely resolved and we are no longer worried every time it rains!
Response from the owner:Hi Fran, we’re so happy to hear this feedback! From the start, our goal was to provide you with a clear, honest assessment of your commercial roof and create a repair plan that would last. Victor’s walkthrough, pointing out problem spots and explaining the process, is exactly how we strive to keep homeowners and property owners informed every step of the way. We’re proud that our roofing team delivered quality craftsmanship that not only fixed the issues but also brought back your peace of mind. You’ve been a pleasure to work with, and we’re truly grateful for your support and trust in Lemus Construction.
Peter S.
3 years ago
Our Management firm has worked with Lemus on various projects over the last 10 years, ranging from full roof and siding replacements on multi-family Condominiums (consisting of 246, 184, 136, and 76 units) to structural facade renovations, window replacements, roof repairs, and everything in between. Not only have we at RCR Management been extremely satisfied with their work quality and response time, but so have the many unit-owners we represent. This company is built on a strong foundation of respectful and caring people, which starts at the top with Victor and Mario. We highly recommend them for any exterior project you may be considering!
Response from the owner:Peter, Thanks for taking the time to submit a great review! Your feedback means the world to us and we really appreciate your kind words. It's always great to receive recognition and your support is invaluable.
Greivin F.
7 years ago
Response from the owner:Thank you for your rating Greivin!
Bernie O.
1 year ago
Lemus approach to our GLV Roofing Project has been spot on from daily management to workers endurance in exceptional heat, especially on the roofs when the heat registered at 130 degrees. I can verify that my Copperfield neighbors came to the aid of Ken’s roofers and ground help. We refilled Gatorade, lemonade, watermelon, cookies, zucchini loaf and even had a chance to treat all of the ground crew to warm sandwiches of BBQ and salad. The crew is respectful and considerate and they clean up every evening. This is just my message but I am sure so many other folks feel so much the same way.
Response from the owner:Hi Bernie, thank you so much for your kind words. We’re thrilled to hear that you’re satisfied with our work and management on the GLV Roofing Project. It’s great to know the crew’s hard work and endurance didn’t go unnoticed, especially in those extreme heat conditions. We appreciate the community support from Copperfield neighbors—it truly makes a difference for our team. Thanks again for your thoughtful feedback!
Michelle S.
3 years ago
Excellent to work with from start to finish! True craftsmen! Very professional- beautiful job!
Response from the owner:Hi Michelle! Thank you for leaving a review. We are honored and humbled by your kind words and look forward to being your go-to for future construction projects you may have.
Tracy C.
4 years ago
Lemus is very responsive, dependable, and THE BEST roofing company that we've used at multiple Residential Homeowner Associations and Condo Associations. They also do a beautiful Job with Deck installation AND window installation!
Response from the owner:Thank you, Tracy! Your review means so much to us. It’s been both a privilege and a pleasure working alongside you and your property management team on townhome and condo projects over the years. From roofing to decking and window installations, we’ve valued every opportunity to support your communities. Your recognition of our dependability and responsiveness means a great deal to our entire team. Long-term partnerships like ours are at the heart of what Lemus Construction does best, and we look forward to continuing to protect and enhance your properties for many years to come.
Diane S.
3 years ago
Lemus Construction is replacing the roofs and gutters in my community. They have been extremely responsive and I am so very pleased with the work done on my home. Highly recommend them!
Response from the owner:Hi Diane, thank you for sharing your positive experience! We will pass along your kind words to the crew.
Karen L.
9 months ago
We recently purchased a new home in Voorhees NJ we had Lemus construction do our new roof all new windows and front door and sliding door . We cannot state how pleased we are with our entire job . Extremely pleased with clear communication , timelines as stated beautiful work by the crew as well as very caring & polite workers . An A plus job all around . Thank you Lemus construction it was a pleasure to have you get us started in our new home . Sincere thanks Tom & Karen Leusner
Response from the owner:Thanks for taking the time to share such a thoughtful review Tom and Karen! We truly appreciate your trust in our team and happy to have played a part in building your new home in this exciting new chapter fornyou both. It was a pleasure working with you, and we wish you many great years ahead in your new home!
Howard A.
9 years ago
Professional, good prices and workmanship that is second to none! Everyone is friendly and work gets done on time and on budget.
Response from the owner:Hi Howard, we strive to provide the highest level of service possible. Thank you for taking the time to share your experience!