Stirling Court Apartments:
Six Buildings, 88 Apartments, and the Work Hiding Behind the Siding
Project Timeline: June 8, 2026 – September 18, 2026
Our Stirling Court siding replacement is renewing the exterior across six multifamily buildings at the 88-unit Stirling Court apartment community in Mount Laurel, New Jersey. We are working directly with Scully Company, with Milton Aguilar managing the project in the field and Eduardo Aguirre supporting operations as demolition, siding installation, window work, capping, carpentry, insulation, and concealed structural repairs move from building to building. The project was scheduled from June through September 2026, giving us a summer-long exterior program that has to keep construction moving while the people inside these apartments continue using the property as home. As of August, the project remains active, with completed sections sitting beside buildings where the exterior is still very much telling us what it needs.
Stirling Court is an established garden-style apartment community at 113A Hastings Way, just off Larchmont Boulevard in Mount Laurel. Scully Company identifies the property as an 88-unit multifamily community and describes its residences as one-bedroom and one-bedroom-with-den apartment homes, with direct access to major South Jersey routes including Route 38 and I-295. Scully acquired the property in 2012, adding it to a regional multifamily portfolio the company has managed and developed for decades. (scullycompany.com)
That context matters because this is not an empty redevelopment site where demolition can spread wherever it pleases. It is an active apartment community with residents coming and going, leasing operations continuing, parking in use, landscaping to protect, and six buildings that cannot all become construction zones at the same time. The exterior needs to change without the community forgetting what it is there for.
Studying the Buildings Before the Walls Started Coming Apart
Our estimating and preconstruction teams began by looking at Stirling Court as a six-building exterior system rather than six identical rectangles. We reviewed siding elevations, windows, exterior trim, wall penetrations, roof transitions, entrances, landscaping, resident routes, equipment access, material staging, dumpster placement, and the places where demolition would expose conditions nobody could fully see from the parking lot. Every building gives up some information during the estimate and keeps some for later.
Those observations moved through our estimating, office, operations, and field teams before Milton began managing active production. Site photographs, measurements, permitting requirements, purchase-order information, building sequencing, and internal notes gave the crews a working map of where the project was headed. Our multifamily siding services are structured around that kind of handoff because the most expensive time to decide how a six-building exterior project should work is usually after three buildings are already open.
The project also required us to look past the broad siding fields. Windows, capping, insulation, studs, sheathing, carpentry, trim, and other wall components all sit inside the same few inches of exterior assembly. Once demolition begins, those trades stop being separate departments and start sharing the same wall.
An 88-Unit Community Managed by Scully Company
Stirling Court is owned and managed within the Scully Company portfolio. Scully describes itself as a full-service multifamily property-management and asset-management company with roots dating to 1948, operating garden-style, mid-rise, and high-rise communities across multiple states. Its management services include maintenance, administration, accounting, reporting, and broader asset oversight, which made the company a direct operating partner on the exterior work rather than simply a name at the bottom of an approval form. (scullycompany.com)
Kristin Bozarth serves as the community manager listed on Stirling Court’s official property page, giving our team a local management connection while work moves through the buildings. Residents received digital start-notice information through the property, while our field and office teams coordinated schedule changes and active work areas as production progressed. The management relationship becomes particularly valuable when one building is nearing finish work while another is still halfway through demolition.
Apartment construction has its own rhythm. Residents are not voting on individual exterior selections the way they might in a condominium association, but they still experience every delivery, saw, lift, dumpster, and temporary access change at ground level. Scully has to keep operating the community while we keep rebuilding it, which means the schedule has to make sense to both sides.
Getting the Mount Laurel Permit Process Moving
Our office also worked through the construction-permit process with Mount Laurel Township. Mount Laurel operates a public UCC construction-permit portal for applications, permit tracking, payments, and inspection-related activity, and the Township requires permitted work to move through the applicable review and inspection process before final closure. (mountlaureltwpnj.portal.fasttrackgov.com)
The permit path was not instantaneous. Our internal project record notes that the Township would not expedite the application, requested an updated scope specifically addressing the siding work, and advised that processing could take up to approximately 20 days. The permit was ultimately paid on July 27, allowing the administrative side of the project to catch up with the production schedule instead of hanging over the remaining buildings indefinitely.
Mount Laurel’s published inspection guidance requires construction work to be inspected under the State Uniform Construction Code and generally calls for advance notification before requested inspections. That means the final stretch cannot simply be judged by how much new siding is visible from the parking lot. Work, inspections, documentation, and permit closeout all need to meet at the same finish line. (mountlaurel.com)
Creating a Jobsite Without Taking Over the Property
The project needed a working construction base before demolition could move efficiently through six occupied buildings. ProGreen provided a 30-yard dumpster, portable restroom, and 8-by-16-foot storage container, giving our crews designated locations for debris, daily needs, tools, and material support. A JCB telehandler was also deployed onsite to assist with the movement of materials and equipment through the active phases.
Temporary infrastructure is one of those things that gets noticed mostly when it is badly placed. A dumpster in the wrong location steals parking, a container in the wrong place blocks access, and a machine parked wherever it happened to stop quickly becomes part of somebody’s morning commute. Our job is to make those pieces support production without convincing the residents that the contractor has annexed the property.
The construction zone therefore has to move. Materials, equipment, crew vehicles, demolition areas, and disposal should stay concentrated around the buildings actually under production rather than spreading across Stirling Court for the entire summer. We need enough room to work correctly and enough discipline to give it back when the building no longer needs us.
Demolition Is Where the Real Exterior Starts Talking
Exterior replacement gets considerably more interesting once the old assembly begins coming off. Until demolition, we can study visible damage, take measurements, review openings, and anticipate likely conditions, but the wall still gets the final vote. Once the existing exterior is removed, concealed sheathing, insulation, framing, and old repairs become part of the actual project instead of the estimate.
That became clear during active production. By August 13, Building 4 demolition was approximately 65% complete, while carpentry, insulation work, stud repairs, and additional wood repairs were progressing alongside it. Those are not decorative upgrades added because the crew ran out of siding to install; they are the kind of concealed conditions that need to be dealt with while access exists and before a finished exterior closes the wall again.
A new siding system can only do so much for a compromised substrate. Covering questionable framing or deteriorated wood because the finished material is waiting on the ground is an excellent way to make the project look complete before it actually is. We would rather have an uncomfortable conversation while the wall is open than a much more expensive one after it is closed.
Carpentry and Stud Repairs Before the Finish Work
The Building 4 field record is particularly useful because it shows how exterior renovation can drift quickly beyond the word “siding.” Carpentry and stud repairs were happening while demolition remained underway, which means the crew was addressing the structure supporting the future exterior rather than simply hanging new material over whatever remained. Insulation work was moving in the same phase, tying energy and wall-cavity conditions into the broader renovation.
That sequencing matters. Framing needs to be sound before exterior sheathing and finished components are asked to depend on it, and insulation needs to be addressed while the cavity is accessible rather than after somebody has installed the last piece of trim. The wall has an order, and fighting that order usually creates rework.
The project record does not yet provide quantified totals for stud replacement, sheathing, insulation, or wood repairs. Those numbers should come from approved field documentation and final closeout records if we decide they are useful for the published story. “A lot” is not a unit of measure, even when demolition makes it feel accurate.
Coordinating Windows With the Exterior Work
Windows also entered the active production sequence. At the August 13 progress checkpoint, Building 3’s window work was recorded as 100% complete, while its siding stood at approximately 85% and exterior capping at 65%. That snapshot shows why windows cannot always be treated as a separate project happening on another calendar.
The opening around a window is one of the most important transitions in an exterior wall. Siding, trim, capping, flashing, sealants, weather-resistive layers, and the window itself all meet within a very small area, and each depends on the next component being installed in the correct order. Our windows and doors services fit naturally into broader exterior projects because the opening has to work with the wall rather than simply occupy a hole in it.
We should not publish a window manufacturer, series, glass package, or unit quantity until the controlling project documents are available. The field tracker confirms window work at Building 3, but it does not give us permission to fill the missing specification with whatever product normally appears on another Lemus job. Accuracy is less exciting than guessing and considerably more useful.
Exterior Capping and the Few Inches Everyone Notices at the End
Building 3’s capping progress was approximately 65% at that same August checkpoint. Exterior capping is one of those scopes that rarely earns the headline but can determine whether windows, trim, fascia, and other exposed details look like they belong to the same renovation. The broad siding field may cover thousands of square feet while a few inches of crooked metal can still be the first thing somebody notices.
Capping also has a practical role beyond appearance. It helps protect specified exterior trim and substrate areas from direct weather exposure when properly detailed and integrated with the surrounding assembly. That means bends, seams, edges, transitions, and terminations deserve the same attention as the larger pieces beside them.
Milton and our field teams have to keep those details consistent from building to building. Six buildings completed over several months should still look like they were part of one capital program when the equipment leaves. The goal is not six interpretations of the same renovation.
Siding Without Inventing the Material Story
The project is, fundamentally, a siding and exterior-renovation program. What we do not yet have in the available documentation is the final manufacturer, siding profile, color, accessory package, weather-resistive barrier, or warranty information. Those specifications belong in the finished case study once the purchase order, proposal, material order, or closeout documents are available.
For now, the more important technical story is the installation process around the material. Our crews are dealing with substrate conditions, insulation, framing, window openings, exterior capping, trim interfaces, and building-specific repair needs before those walls reach finished condition. Our exterior renovation services are built around that broader view because siding is the visible part of the assembly, not the entire assembly.
The final manufacturer information will matter. It will tell us how the product needs to move, fasten, drain, terminate, and be maintained over time. Until we have that information, pretending a product name into existence would make the page more detailed and the project record less accurate.
Building 3 Shows What the Finish Line Looks Like
The August 13 status for Building 3 gave us one of the clearest mid-project snapshots. Siding was approximately 85% complete, the associated window work had reached 100%, and exterior capping was approximately 65%. That meant the building was far enough along to show the direction of the finished exterior while still carrying several details needed before anyone could call it done.
Those late-stage details are exactly where a long project can lose patience. Once most of the wall is covered, the temptation is to look toward the next building and treat the remaining trim, capping, penetrations, cleanup, and corrections as somebody else’s small problem. Small problems have a habit of forming the punch list.
Our field supervision keeps those remaining conditions tied to the building before the crews move too far away. Matching materials, access equipment, and people familiar with the work are easiest to use while they are still standing nearby. Returning two months later to fix six forgotten details is a much worse system.
Building 4 Shows Why No Two Buildings Are Truly the Same
Building 4 was at a very different point during the same August update. Demolition was about 65% complete, with carpentry, insulation, stud repairs, and additional wood repairs progressing while the walls remained open. Two adjacent phases of the same project were therefore telling completely different stories on the same day.
That is why we do not treat six multifamily buildings like six copies of one estimate. One building may be moving through finish capping while the next is exposing concealed framing that needs additional work before the exterior can move forward. The schedule needs enough structure to keep everyone moving and enough flexibility to admit when a wall has changed the plan.
That difference also affects communication with Scully. A percentage complete for the project does not tell management which residents are experiencing demolition and which are looking at nearly finished elevations. Building-level reporting gives everybody a better picture of what is actually happening on the ground.
Maintaining Resident Access While Construction Moves
Stirling Court remained occupied throughout the renovation. Residents still needed to leave for work, carry groceries inside, walk pets, receive deliveries, meet visitors, and use the property while our crews were opening and rebuilding exterior walls nearby. Those routines do not become less important because a lift happens to be parked outside.
Digital start notices provided through the property helped residents understand when active work was approaching. Our team also had to coordinate access zones, equipment placement, dumpsters, material staging, and temporary restrictions so residents were not left guessing which part of the property would be affected next. The best resident communication usually answers a simple question: what changes for me tomorrow?
Daily organization matters just as much as the notices. Loose debris, exposed materials, tools, fasteners, packaging, and construction equipment have to stay controlled around an occupied apartment property. Residents will tolerate noise for a capital project; they are less forgiving when the noise comes with an obstacle course.
Working With a Property That Never Stops Operating
Scully continues to lease and manage Stirling Court while the renovation moves through the property. The official community page remains active with apartment availability, leasing contact information, amenities, and resident services throughout construction. That operating reality changes how we think about the jobsite because the finished product is not the only thing representing the property while work is underway. (scullycompany.com)
Prospective residents can still arrive. Current residents still judge how the community is being maintained. Ownership and management still need the property to look controlled enough that renovation reads as investment rather than disorder.
That is part of what makes multifamily exterior work different from an isolated vacant-building renovation. The asset has to continue functioning while we improve it. Construction does not get to wait for a convenient moment when nobody lives there.
Permit Delays Do Not Mean Production Can Stop Thinking Ahead
The Mount Laurel permit timeline required patience early in the project. Our internal notes show the Township requested a siding-specific scope update and would not expedite processing, with the permit ultimately paid in late July. That kind of delay can create a temptation to treat every later scheduling issue as the permit’s fault.
The better approach is to keep the parts we control moving. Materials, building sequencing, resident communication, staging plans, field documentation, and production readiness can still be organized while administrative items are being resolved. When the permit catches up, the project should be ready to use it.
That discipline becomes increasingly important as the September target approaches. A schedule recovering from early administrative delay has less room for poorly coordinated deliveries or incomplete building information later. The calendar does not care why the earlier days disappeared.
What Residents Should Expect From the Renewed Exterior
Residents in completed buildings should expect a cleaner, more consistent facade, renewed window and trim transitions where included, and exterior components installed over repaired conditions rather than simply covering whatever demolition uncovered. They should also expect the exterior to remain an actively maintained building system after construction ends. New materials reduce maintenance pressure; they do not eliminate weather, impacts, landscaping, moisture, or future service work.
Residents can help by reporting loose siding, damaged trim, staining, movement around window openings, recurring water marks, or exterior changes after severe weather. They should not drill through managed exterior components for cameras, decorations, satellite equipment, or other attachments without approval from Scully. One small penetration made without understanding the wall assembly can become somebody else’s much larger investigation later.
Landscaping should also stay clear enough that lower wall areas can dry and remain visible for inspection. Sprinklers should not repeatedly wet the same facade areas, and shrubs should not rub against siding or trim every time the wind moves them. Exterior materials age much better when the landscaping is not quietly trying to dismantle them.
What Scully Should Carry Into Long-Term Maintenance
Once the project reaches closeout, Scully should maintain building-specific records for all six structures. The final file should include the purchase orders, material specifications, approved colors, window information, permit records, inspection approvals, photographs, concealed-condition repairs, insulation and framing documentation, change orders, punch lists, warranty documents, and future service history. An 88-unit property is manageable with organized records and surprisingly mysterious without them.
Periodic exterior inspections should review siding, capping, trim, windows, sealants, penetrations, lower-wall clearances, roof-to-wall intersections, drainage patterns, and any areas altered by later contractors. Building 4’s concealed repairs should be documented particularly well because future management teams should know where structural or substrate conditions were corrected during the 2026 program. The best future inspection starts with knowing what happened the last time the wall was open.
Scully should also control future penetrations and exterior modifications. Cable, security, HVAC, electrical, pest-control, signage, and other contractors should document where they are fastening equipment and how the surrounding water-management details will be restored. The exterior should not become a community bulletin board for every trade that arrives with screws.
Warranty documents should be added to the property record once the final manufacturer and coverage information is confirmed. Our warranty information can provide general guidance, but the Stirling Court product registrations and issued project documents should control future repair decisions. Guessing at warranty coverage is particularly unhelpful when someone needs to make an actual claim.
Six Buildings, One Property, and a Better Exterior Baseline
The Stirling Court project is bringing together six multifamily buildings at an 88-unit apartment community, active siding replacement, window coordination, exterior capping, insulation work, carpentry, stud repairs, additional wood repairs, Mount Laurel permits, heavy equipment, resident notices, and months of phased construction. Milton, Eduardo, our estimating team, office staff, crews, and Scully’s property-management team each have a different part of that work to control as the project moves toward its September target. The finished siding will eventually be the easiest thing to see, but the conditions repaired behind it are a large part of what will determine whether the investment holds up.
The work is still underway, so the final story should wait for the final facts. Once the six-building program is complete, we can add the approved siding system, window specifications, warranty information, actual completion date, final repair quantities, inspections, and any other closeout details that deserve to become part of the permanent record. That will turn an active construction story into a complete case study rather than a progress report dressed up like one.
Stirling Court will then join our growing collection of completed multifamily exterior projects throughout New Jersey, Pennsylvania, and the Mid-Atlantic. Apartment owners and property managers planning siding, windows, roofing, decks, drainage, or broader building-envelope work need a contractor prepared to manage the asset while residents continue living inside it. That means thinking about the wall, the schedule, the paperwork, and the people at the same time.
Planning a siding replacement or broader exterior renovation for an apartment community, condominium, HOA, or multifamily portfolio? Contact Lemus Construction to discuss your buildings, phasing strategy, resident communication, concealed-condition planning, permits, warranties, and long-term exterior maintenance.